Should You Refinish Your Floors Before or After Painting?

Short answer: refinish your floors first, then paint. Floor sanding is messy. The dust, the stain and the finish all end up on walls and baseboards. If the painting is done last, the painter cleans up that mess and leaves everything fresh. If the painting is done first, you often pay to redo part of it.
There is one exception. If your walls need major plaster repairs, those should be done before the floors. Here is how we plan it on our interior painting jobs in Montreal and Westmount.
Why floors should come before paint
Sanding a hardwood floor creates fine dust that travels everywhere. Vacuum systems on the sanders help, but they never catch it all.
If the walls were just painted, that dust settles on them. The floor crew may also leave hand marks on the walls, or overspray from their finish.
Baseboards take the worst of it. Freshly painted white baseboards and quarter rounds get scuffed by the sanders and splashed with stain. They then need to be repaired, replaced or repainted. That is paying twice for the same work.
When painting comes last, none of this matters. We wash the dust off the walls, cover any marks or overspray, and paint the baseboards once, cleanly.
The exception: big plaster repairs come first
Plaster repairs mean sanding compound and dropping debris. Even with the floor covered, fine dust can slip under the protection and settle into the gaps between floorboards.
On a floor that is about to be sanded, that is not a problem. The floor crew sands it all away. On a floor that was just refinished, it is. So when a house needs serious plaster work, we do it before the floor company arrives, then come back to paint once the floors are done.
The right order for a full renovation
- Electrical work, and any kitchen or demolition work
- Plaster and drywall repairs
- Floor sanding and refinishing
- Painting: walls, ceilings, trim and baseboards
- New carpet, if any
Will painting damage your new floors?
Not if they are protected properly. Modern floor finishes are ready quickly, and we can usually work on them within the same week. Your floor company will confirm when it's safe.
We tape along the baseboards with a high-quality painter's tape that won't pull up the finish. We then cover the whole floor in plastic, with tarps on top where we set down ladders and paint cans. The plastic stops dust and paint. The tarps stop scuffs.
We were careful about tape the first time too. The floor contractor told us that with a well-applied finish, such as Bona, good tape is safe. That has held true on our jobs. And if a drip of fresh paint ever reaches the floor, it wipes off with warm water and a bit of soap without harming the finish.
Can floors and painting happen in the same week?
Yes, when a deadline requires it. On one project, we did the plaster repairs first while the client held off the floor company. We then moved to a floor that wasn't getting refinished, and handed the first floor over to the floor crew.
The floor crew took about a week. We sealed their floor off with a large plastic wall and a zip door, so their dust stayed on their side. Once they told us it was ready, we moved back in and finished. Both companies stayed on schedule.
It works, but it takes coordination between the two contractors.
What about electrical work, kitchens and carpet?
Electrical work always comes before painting. Electricians open walls to run cables and cut holes in ceilings for new lights. Ceilings get handled with work gloves, and fingerprints on a flat ceiling don't wash off easily. Their work almost always leaves plaster or drywall repairs too, and a patched wall needs to be repainted in full, not touched up in one spot.
Kitchens and demolition come first for the same reason. Removing cabinets and opening walls makes a lot of mess.
Carpet can go in after painting. If you can, remove the old carpet before we start. Install the new one once we're done, so there's no chance of paint on it.
Hiring the floor company and the painter separately?
- Find out early if your walls need plaster repairs. That decides the order.
- Give each contractor the other's number and ask them to talk. They'll sort out the schedule faster than anyone.
- If you just bought the house and have access before moving in, that's the best time to do plaster repairs, before the floors.
Planning a renovation and not sure about the order? We're happy to look at your project and help you plan it. Learn more about our interior painting services in Montreal and Westmount.